Bathroom Renovation - 100 HARRIS ST : Job Done with Houseace
Jon's Project
100 HARRIS ST
What We Did

Bathroom Renovation
Free Quote
How It Went

  • Design and Ordering - 5 Days

    Setup of important site information, finalise and order product and finishes.

  • Demolition and preparation

    Strip out stage, remove all fixtures set out bathroom and inspect

  • Framing - 2 Days

  • Pipe out and Pre wire 1 day

  • Lining and Water Proofing - 2-3 days

  • Tiling and painting - 4-6 Days

  • Finishes and Fitoff - 2 Days

  • Clean and Handover - 1 day